Deferral Template/ Code

(4) ShareShare
ReportReport
Posted on by 116
Hi Community,
 
Was wondering if any of you have documentation on how to set up User Defined - Calculation Method of Deferral Template? This is the documentation that's available but its more of a general guidance. 
 
 
Thank you!
I have the same question (0)
  • Suggested answer
    AndrewThomas81 Profile Picture
    496 on at
    User-Defined: The periodic deferral amounts aren't calculated. You must manually fill the Amount field for each period in the Deferral Schedule page. 
     
    So when using the deferral template, the user will need to open the deferral schedule on each line and manually enter the amounts.
     
  • Suggested answer
    Rajvi Shah Profile Picture
    123 on at
    Hello,
     
    You can use below step-by-step process:
    Calculation Method on the Deferral Code is User Defined.
    Field Value
    Deferral Code e.g., MANUAL
    Description Manual Revenue Deferral
    Deferral Account Your G/L Liability Account
    Deferral % 100
    Calc. Method User-Defined
    Start Date Posting Date
    No. of Periods 2
    Period Desc. Deferral Revenue for the month of %4 in %6
     
     
     
    In the Invoice you need to define the deferral code.
    From Deferral Schedule option available at 3 dot on the right side of the deferral code field, you can define the amount manual.
     
    Regards,
    Rajvi Shah
  • Suggested answer
    Ahmad Subhani Profile Picture
    636 on at
    Hi,
     
    Please check this Article for relevant details.
     
  • Suggested answer
    Teagen Boll Profile Picture
    1,436 Super User 2026 Season 1 on at
    If you use the User Defined method you then need to manually setup your deferral amounts in the deferral schedule. Below is an example:
    You want to make sure your Amount to defer matches the lines as well. Once thats done you're good to go. 
     
    Best,
    Teagen
    Catapult ERP
     
  • Suggested answer
    OussamaSabbouh Profile Picture
    12,965 Super User 2026 Season 1 on at
    Hello,
    The Microsoft docs are pretty much the full story here: in Business Central, User-Defined on a Deferral Template does not give you a special setup method or formula — it just means BC won’t calculate the deferral amounts automatically, so you create the template with Calc. Method = User-Defined, apply it to the G/L account/item/resource or document line, then open Deferral Schedule and manually enter or adjust the Amount per period before posting; so if you were looking for extra Microsoft documentation with a separate configuration process, there really isn’t much beyond that, because this option is basically the manual fallback when Straight-Line, Equal per Period, or Days per Period don’t fit.
    Regards,
    Oussama Sabbouh

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the March Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
OussamaSabbouh Profile Picture

OussamaSabbouh 1,993 Super User 2026 Season 1

#2
YUN ZHU Profile Picture

YUN ZHU 1,116 Super User 2026 Season 1

#3
Khushbu Rajvi. Profile Picture

Khushbu Rajvi. 557 Super User 2026 Season 1

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans