Project Budget

(1) ShareShare
ReportReport
Posted on by 82
Hi, 
 
We have "Central AC Installation projects", according to the project nature we couldn't update the budget when we get the contract signed by the client, because we will have so many variations till "Duct Installation" stage, otherwise we will create so many revisions to the project budget. therefore, we create the project budget upon that stage, the main issue is : there is some actual costs incurred & booked before that stage "about 10% of the project budget" subsequently before Budget creation!
Later when I check the variances using "project budget balances" [Control >Control > project budget balances] , the (Per-budget creation actual costs) were not reflected in "Consumed budget" 
 
Is there any solution to include the (Per-budget creation actual costs) in this inquiry/ report?
 
Rgds
Mostafa Nagy
Project Budget Balances.png
Categories:
I have the same question (0)
  • Verified answer
    Abhilash Warrier Profile Picture
    7,454 Super User 2026 Season 1 on at
    Yes you are right,  you will be required to create an initial budget at project start and revise it later — this ensures all future actuals are consumed against the budget.
     
    Else, 
    • Project actuals show all costs, including those posted before the budget was created.
    • Consumed budget shows only costs posted after the budget was approved.
    • Since early costs happened before the budget, they cannot appear in Consumed budget.
    For full historical visibility:
    1. Use Project actuals to see early (pre‑budget) costs.
    2. Use Consumed budget to see costs after budget approval.
    3. Optionally, use a  custom report to combine both into one clear view of total project cost vs budget.
     
  • Mustafa Quraitem Profile Picture
    82 on at
     
     
    Great thanks for your answer, I will create the project budget from project DAY1 but I will select "Allow overruns" for "Budget overrun default"  till I get the final budget then I will update it as a revision 
     
    Regards
    Mostafa 

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the March Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Giorgio Bonacorsi Profile Picture

Giorgio Bonacorsi 657

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 615 Super User 2026 Season 1

#3
CP04-islander Profile Picture

CP04-islander 356

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans