Gantt Chart Scheduling Issue – Operation Not Splitting Across Resources

(0) ShareShare
ReportReport
Posted on by 67

Hello Everyone,

Appreciate your help!

In the Gantt chart, Operation 30 requires 10 hours of processing time. However, the system is assigning only one resource from the capability and scheduling it according to a single day shift, instead of splitting the operation across two resources. As a result, the operation appears to take longer than it actually does in practice.

On the ground, once one resource’s shift ends, another resource takes over. Shouldn’t the system split the operation between two resources?

I would appreciate if someone can help or share suggestions on how to resolve this issue.

I have the same question (0)
  • André Arnaud de Calavon Profile Picture
    300,968 Super User 2025 Season 2 on at
    Hi Anthony,
     
    Is your scenario that the operation can be split to be performed by 2 people in parallel? Or are you expecting that the job planning is aware of shifts and try to plan two resources consecutive? Note that the job scheduling can't split jobs.
  • Anthony Maroun Profile Picture
    67 on at
     
    I expected that the job planning will be aware of shifts and split the secondary operations which is Laborer into shifts, because the machine (Primary Operation) operates 24/7 during the week and the laborers (Secondary Operation) works as shifts that works on the machine. If the job scheduling Can't split jobs, do u have any alternative solution for the process to work as it will affect the Master planning by not splitting.
     
    Appreciate your help as always.
     
    Regards 
  • André Arnaud de Calavon Profile Picture
    300,968 Super User 2025 Season 2 on at
    Hi Anthony,
     
    Very honest, I have not came across your requirement before. As far as I know, the scheduling is not capable of splitting the jobs. Do you have each shift as separate resources?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
Laurens vd Tang Profile Picture

Laurens vd Tang 231 Super User 2025 Season 2

#2
Siv Sagar Profile Picture

Siv Sagar 228 Super User 2025 Season 2

#3
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 125 Super User 2025 Season 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans